Hi - I have a few files. One starts with timesteps 4,5,6,...another starts with 2,3,4 another starts with 21,22,23,24. I want to change them so they all start with timestep 0,1,2,3,4...how can I do that? Thanks, Sarah.


Replies (1)

RE: CDO set timesteps - Added by Ralf Mueller about 5 years ago

Hi Sarah!

is this still an issue? For time axis properties you can use the settaxis operator. In case you still have trouble please upload the file.