Project

General

Profile

CDO set timesteps

Added by Sarah O'Keefe over 5 years ago

Hi - I have a few files. One starts with timesteps 4,5,6,...another starts with 2,3,4 another starts with 21,22,23,24. I want to change them so they all start with timestep 0,1,2,3,4...how can I do that? Thanks, Sarah.


Replies (1)

RE: CDO set timesteps - Added by Ralf Mueller over 5 years ago

Hi Sarah!

is this still an issue? For time axis properties you can use the settaxis operator. In case you still have trouble please upload the file.

cheers
ralf

    (1-1/1)